Site: Gude Panchgani (Gotne)
State: Maharashtra
Site Capacity: 24 MW (16x1.5 MW, Suzlon S82_78.5M Hub Height)
Nearest Major Town: Satara
Nearest Airport: Kohlapur
Height above Mean Sea level: 1000 m
Land Type: Forest
Feed in tariff: Rs 5.67 /kWh
PPA: 13 yrs
Project approval from State Nodal Agency: April 2007
Power Evacuation: Approved
Expected date of commissioning: September 2012